Cases /
Smart Energy Meter Case Study: Sub-Metering a Cabinet With No Space Left

Smart Energy Meter Case Study: Sub-Metering a Cabinet With No Space Left

A tower retrofit required tenant submetering but no space was available in the panels. Four-module DIN meters and one gateway per floor solved it.
2026/11/25
Reading volume: 0

Case Details

Smart Energy Meter Case Study: Sub-Metering a Cabinet With No Space Left

A retrofit contractor was asked to add tenant sub-metering to a twelve-floor office tower that was already occupied. Every floor board had two or three free module spaces and no room for a new enclosure, and the landlord wanted billing data within the quarter. We supplied four-module DIN rail meters with a single gateway per floor, and the whole building was commissioned in eighteen days without a board change.

Project Snapshot

The Problem: An Occupied Building and a Board With No Room

The tower was built with one meter per floor and no sub-metering. Tenants were billed on floor area, which worked until the floors were split, and then the landlord started carrying the cost of the common areas on top of a dispute about who ran what.

Physically, there was nowhere to put anything. Floor boards were full, the riser had no spare way, and the riser cupboard door opened onto a corridor the tenants used.

The commercial constraint was tighter than the physical one. The building was occupied, so every floor needed power, and a shutdown window measured in hours per floor was all the tenants would accept.

Why We Chose Four-Module DIN Meters Over Panel Meters, Direct Cellular Meters and External CT Cabinets

Panel cut-out meters with a display bezel. Excluded. They need a door cut, a new enclosure or both, and every cut is a shutdown and a re-certification of the board.

One cellular meter per point, each with its own SIM. Excluded. Metal riser cupboards attenuate badly, and 96 subscriptions is a cost and an admin burden that scales badly.

External CT cabinets beside each board. Excluded. There is no wall space in the cupboard, and the extra wiring makes the fault-finding worse.

Four-module DIN rail meters with one gateway per floor. Selected. The meter fits the free space, and the gateway handles the uplink for the whole floor.

The Meters We Built

Each tenancy point took a four-module three-phase meter on the standard 18 mm pitch, direct connected at 5(60) A where the supply allowed and CT-fed where the tenancy load was larger. Four modules is the difference between fitting the gap and not fitting it, and the whole design started from that number.

Communication is split. Meters talk to the floor gateway over LoRa, which reaches through a metal cupboard because the gateway sits inside it. The gateway talks to the cloud over 4G, so no building network and no tenant IT approval was needed. Our 4G three-phase DIN rail meter covers the cases where a point is far from the riser and needs its own uplink.

Load profiles are stored at 15-minute intervals and pushed to the platform, which is the granularity the landlord's billing system consumes. The power data gateway buffers locally, so a lost uplink does not mean a lost interval.

Installation: How the Work Ran

Work ran one floor at a time, top down, on a night window.

Each floor took roughly a day and a half. The night shift isolated the board, fitted the meters and CTs, and restored power before morning. The following day was spent joining the meters to the gateway and checking the first intervals against a clamp meter.

Because the gateway carries the uplink, tenant IT was never involved. That removed the step that usually holds this kind of retrofit for weeks. The standard DIN installation sequence was followed without change on every floor, which is what kept the pace.

Testing and Quality Control

Every meter is calibrated and function-tested at the factory before packing, and the meter identity, firmware version and calibration record travel with the carton.

On site, commissioning compared each meter reading against a reference clamp meter at load, and any point outside the agreed band was re-checked before the floor was signed off. Interval data was validated for completeness, not just for presence, so gaps in a profile were caught on the night they happened rather than at the first bill run.

Gateway buffering was tested deliberately by pulling the uplink for a floor and confirming the intervals arrived intact afterwards.

Results: What the Numbers Show

All 96 points were commissioned inside eighteen days with no board replaced and no tenant moved out. The first bill run went out on the platform's 15-minute profile, and the landlord retired the floor-area allocation that had been driving the dispute.

Common-area cost stopped being an argument, because it is now measured rather than apportioned. The contractor has since quoted the same arrangement on two further buildings.

The 4G DIN meter range covers the same job where a riser is too far from the gateway, and the platform accepts both architectures on one account.

What This Case Means for Your Project

Retrofit sub-metering is a space problem before it is a metering problem. Count the free modules on the board first, and the whole design follows from what you find.

Send us the board layout, the number of points per floor and the load at each one. We will propose a meter width that fits, size the gateway count, and quote the package with the interval data format your billing system needs. You can brief our engineering team on the riser drawings directly.

Item

Detail

Client

Retrofit electrical contractor and panel builder

Site

Twelve-floor occupied office tower, 96 tenancy areas

Project

Tenant sub-metering retrofit without board replacement

Products

Three-phase DIN rail meters, current transformers, data gateways

Material and finish

Flame-retardant polycarbonate case, sealed terminal cover

Load range

5(60) A direct connected, CT-fed variants to 250 A

Factory lead time

22 days from specification approval to shipment

On-site time

18 days of installation, commissioning and data validation

Outcome

96 points billed on a 15-minute load profile, no board replaced